5 Year Housing Land Supply Report 2025

APPENDIX C - Additional Evidence acquired and assumptions in regard to delivery of large sites over the next 5 years

SITE Evidence of
Delivery ref. 
no.
EVIDENCE + ASSUMPTIONS
Spout Farm, Preston Road, 
Longridge
EV6

Application 3/2016/0580 was granted full permission in May 2017 for the development of 34 houses. Development is nearly completed, with our records indicating there are just 2 properties remaining to be completed.

The authority expects both properties to be completed within 5 years

Land East of Chipping Lane, 
Longridge, Preston – Phases 
2 & 3
EV7

Reserved matters application was granted for the development of 193 dwellings in April 2019 through planning application 3/2018/0975. This was increased to 198 dwellings. Development is under way and our records indicate there are 35 dwellings remaining to be completed.

The authority expects all 35 dwellings to be completed within the next 5 years

Lawsonsteads, Whalley 
(Phase 2)
EV8

Application 3/2018/0914 granted full consent for the development of 188 dwellings in September 2019. Development has commenced and our records indicate that 55 dwellings have been completed. 133 dwellings remain. The developer (Lovell) expects the site to be completed by March 2027.

The authority therefore expects all 83 dwellings to be completed within 5 years

Oakhill College, Wiswell 
Lane, Whalley
EV9

Since the approval of the full application for 8 dwellings (3/2019/1124), the application was re-submitted and approved on 13th January 2021 to account for the amendment of the house type of Plot 7. Our records indicate there is still one property to be completed.

The authority expects this remaining dwelling to be completed within 5 years

Standen, Phases 2, 3 & 4; 
Land at Pendle Road, 
Clitheroe
EV10

Reserved matters application 3/2019/0953 granted permission for 426 dwellings in March 2020. Development is now under way on this site and our records indicate that 294 dwellings remain to be completed. Evidence received from Taylor Wimpey supports the assumption development will be completed within 5 years.

The authority therefore expects all remaining dwellings to be completed within 5 years

Standen, Phases 5 & 6, Land 
at Pendle Road, Clitheroe
EV14

Outline planning permission granted permission for 1040 residential dwellings in total. There is currently a full planning application under consideration which details 265 dwellings on these two phases. 

On the basis that the developer has confirmed that phases 2, 3 and 4 will be completed in the next 5 years and in line with completion rates on previous phases of the development the authority anticipates 41 dwellings will be completed from April 29 on these phases.

Land South West & West of 
Whalley Road, Barrow –
Parcel B
EV19

Full consent was granted in September 2019 for 233 dwellings on Parcel B of this development through planning application 3/2019/0012. This is part of the larger site granted permission under application 3/2012/0630. Development is nearly completed and our records indicate there are 8 dwellings remaining to be completed.

The authority expect both of these dwellings to be completed within the next 5 years.

Land off Dale View, Billington, 
Clitheroe
EV20

Reserved matters application was approved in January 2000 for 49 dwellings. 35 of these dwellings have been completed. There are 14 dwellings remaining to be completed. 

Due to the length of time this development has stalled the council does not expect any of these 14 remaining dwellings to be completed in the next 5 years.

Chapel Hill, Hill Barn Drive, 
Longridge, Preston
EV36

Full consent was granted in November 2012 with application 3/2011/1071. The site has been the subject of delays in development however most if not all units are largely under construction. Our records indicate that there are 30 remaining dwellings to be completed on this site.

The authority expects all remaining 30 dwellings to be completed within the next 5 years.

Land East of Chipping Lane, 
Longridge – Phase 1
EV37

Reserved matters was approved in September 2019 for 124 dwellings through planning application 3/2018/0404. Development has nearly been completed on this phase of the development, with our records indicating there are only 5 dwellings remaining to be completed.

The authority expects all remaining 5 dwellings to be completed within the next 5 years.

Land West of Preston Road, 
Longridge
EV39

Reserved matters application 3/2018/0105 was approved in May 2018 for 275 dwellings. Development is underway on site and our records indicate there are 95 dwellings still to be constructed.

The authority expects all 95 dwellings to be completed within the next 5 years.

Plot 4 Cherry Drive, Brockhall 
Village, Old Langho
EV42

Application for full consent was granted in March 2020 through planning application 3/2020/0050 for one property. Our records indicate this property has not yet been completed.

The authority expects this dwelling to be completed within the next 5 years.

Land at Hillside, Brockhall 
Village, Old Langho
EV43

Application for full consent was granted back in 3/2010/0387 for one dwelling. Our records indicate this dwelling is still to be completed.

The authority expects this dwelling to be completed within the next 5 years.

The Moorcock Inn, Slaidburn 
Road, Waddington
EV46

Full consent was granted in May 2018 through application 3/2018/0344 for four dwellings. This amended application 3/2017/0674 which was for the same no. of dwellings. Three dwellings have now been completed, leaving just one remaining dwelling.

The authority expects the remaining dwelling to be completed within the next 5 years.

Land at Accrington Road, 
Whalley
EV47

Reserved matters application 3/2016/0344 granted permission for 77 dwellings, which is an extant permission. Information from the agent suggests delivery could start from 2026 and the authority considers completions from 2027/28 at a rate of 20 completions per year to be a reasonable estimate.

The authority expects 60 dwellings to be completed within the next five years.

Land at Wilpshire (Land East 
of Salesbury View)
EV49 Following a recent appeal decision on this site (3/2023/0614) 75 units is considered to be a reasonable estimate.
Land off Hawthorne Place, 
Clitheroe
EV51

Full consent was granted in December 21 with application 3/2019/1104 for the erection of 58 dwellings. A non material amendment in February 2022 (application 3/2022/0087) reduced this to 57 dwellings. Development has commenced on this site and our records indicate there are 19 dwellings remaining to be completed.

The authority expects all 19 remaining dwellings to be completed within the next 5 years.

Land at Highmoor Farm, 
Clitheroe
EV52

Application 3/2020/0601 granted outline consent in February 2023 for up to 125 dwellings. Development has not yet commenced on site, however evidence from the planning agent suggests completions from 2027/28 averaging 25 houses per annum.

The authority therefore expects 75 dwellings to be completed within the next 5 years.

Land South of Laycocks Farm, 
Langho
EV53 Application 3/2022/0537 granted full consent in April 2023 for the construction of 8 dwellings. This development is now under way.
Brockhall Farm, Brockhall 
Village, Od Langho, 
Blackburn, BB6 8BB
EV55

Application 3/2021/0311 granted full consent in August 2021 for the demolition and conversion of several agricultural buildings into 8 residential properties. 

The authority expects all 8 dwellings to be completed within the next 5 years.

Land at Neddy Lane, 
Billington, Clitheroe, BB7 9LL
EV58

Full consent was granted in October 2022 for 36 dwellings through application 3/2021/0205. Development has commenced on site.

The authority expects the remaining 17 dwellings to be completed within the next five year.

74 Higher Road and land to 
the rear, Longridge, Preston, 
PR3 3SY
EV59

Reserved matters application 3/2021/0556 was approved in May 2022 for the erection of 123 dwellings and demolition of 74 Higher Road (Net gain 122 dwellings). There has been a technical start made on site. Information from Onward Homes confirms completions will be after March 2026.

The authority expects 122 dwellings to be completed within the next 5 years.

Crow Trees Farm, Chatburn EV62

Site has full permission for 37 dwellings through planning application 3/2022/0966.

The authority expects all 37 of these dwellings to be completed within 5 year.

Tan Yard Farm, Hothersall EV63

Site has full permission and the development through planning application 3/2023/0075 for 2 dwellings.

The authority expects both dwellings to be completed within the next 5 years.

Pendle Mill, Clitheroe EV64

Outline permission has been granted through planning application 3/2024/0327 for a 75 bed care home.

The council expects the care home to be completed within the next 5 years.